Global Change in Primavera P6 doesn't add Resources

Similar to Global Change in P3, Want to add a resource to all activities using global change. Can't seem to figure out how to do it.

Posted by on

Ad

1 Answer

  • Level 1:

    An expert who has achieved level 1.

  • Contributor
  • 1 Answer

How to use primavera global change

Posted on Apr 22, 2009

Ad

1 Suggested Answer

6ya6ya
  • 2 Answers

SOURCE: I have freestanding Series 8 dishwasher. Lately during the filling cycle water hammer is occurring. How can this be resolved

Hi there,
Save hours of searching online or wasting money on unnecessary repairs by talking to a 6YA Expert who can help you resolve this issue over the phone in a minute or two.

Best thing about this new service is that you are never placed on hold and get to talk to real repairmen in the US.

Here's a link to this great service

Good luck!

Posted on Jan 02, 2017

Ad

Add Your Answer

Uploading: 0%

my-video-file.mp4

Complete. Click "Add" to insert your video. Add

×

Loading...
Loading...

Related Questions:

1 Answer

Does primavera 3 works on win 8 ??


There are a lot of questions about this, without any answers! So I guess the answer is 'No'
It seems you would need to install both versions P6 and P3 on Win 8 then export P3 files to P6 to run, but even that isn't easy.

Jan 24, 2014 | Primavera Project Planner P3 (PRIMAVERAP3)...

1 Answer

76csx I CAN'T ACCES THE MAPS ON THE GPS OR THE CARD


Features on the phone device makes compatibility to media attainable among several innovative functionalities. The phone in question least has an extensive capacity to display the entire global mapping program. For example, multimedia resources either as maps, picture grams require an expansive device components to capture display for experiences. The mobile phone in question as manufactures default only provides telecommunication resources with feature observation of media impressions. Acquiring an alternate device that has an extensive expectation would provide the requested impressions. For example, the entire global position device would provide experiences as manufacturers default. Also, computers either as desktop or notebooks provide the entire experience of telephony among several features of multimedia impressions similar to global position system programs. Computers however are multifunction's devices, also versatile that captures displays and manipulates resources.

Feb 25, 2011 | Garmin GPSMAP 76CSx Handheld GPS GPS...

2 Answers

My Primavera P6 is not letting me export it to a P3. That line is greyed out. Any other suggestions to get it exported to a P3?


You could get your administrator to give you rights to export or since that isnt likely you can bring up all of your columns copy and paste to a excel file that was created from P3. It's messy and you'll loose all your logic ties, but it's the only way I've every beaten the man.

Jul 10, 2009 | Computers & Internet

1 Answer

P5 tutorial


i am a p3 user i want to use p6 but i dont understant how to use for that i need p6 tutorial so that i can use p6 easily

Jun 25, 2009 | Primavera Project Planner P3 (PRIMAVERAP3)...

1 Answer

Activity ID changes in P6


Select all the activities you would like to Edit (All or Portions)
'right click' in that menu there is an option that says Renumber activity ID's select that and choose the new prefix/suffix/Identifier and P6 will renumber them all in sequence. I use 3 letters as my prefix for smart coded IDs example (DCS1000) or (DCS-1000) for the DCS system. Visually easier to see and can be used as a filter point (Act ID Contains DCS) anyway I hope this helps...

Jun 09, 2009 | Primavera Contractor 6.1 Full Version for...

1 Answer

Importing MSP Files into P6


There is a simple solution to import mpp files into P6.

Please contact me.
Boruziniyat@gmail.com

Oct 22, 2008 | Computers & Internet

3 Answers

Primavera P6


I am new in P6. I have a problem that how can we add target in any project like P3? Can u please help me.

Jun 20, 2008 | Primavera Computers & Internet

Not finding what you are looking for?
Computers & Internet Logo

Related Topics:

1,105 people viewed this question

Ask a Question

Usually answered in minutes!

Top Computers & Internet Experts

Les Dickinson
Les Dickinson

Level 3 Expert

18425 Answers

Alun Cox

Level 3 Expert

2678 Answers

David Payne
David Payne

Level 3 Expert

14162 Answers

Are you a Computer and Internet Expert? Answer questions, earn points and help others

Answer questions

Manuals & User Guides

Loading...